Milton Park
Tree Pruning in Milton Park
Action: Remove epicormic growth, thin crown and raise canopy where required by 16/05/08
Officer responsible: Bob McLeish
Task completed
No Golf Practice sign
Action: Replace damaged sign by 16/05/08
Officer responsible: Bob McLeish
Task completed
No Dog Fouling signs
Action: Clean sign by 16/05/08
Officer responsible: Bob McLeish
Task completed
Pathway
Action: None all paths have been sprayed with herbicide, clear evidence of die back on vegetation.
Play Equipment
Action: upgrading of this play site and equipment forms part of the playground development plan which is subject to capital funding being made available.
Banks of the burn
Action: The vegetation is left long for safety reasons i.e. to deter children from accessing the burn particularly when in spate.
There is a small pocket of Japanese knotweed which will be treated with aquatic approved herbicide by 16/05/08 subject to suitable weather conditions.
Officer responsible: Bob McLeish
Task completed
Old Notice Board
Action: remove board by 16/05/08.
Officer responsible: Bob McLeish
Task completed
Milton Brae
Trees overhanging pavement
Action, Remove overhanging vegetation by 16/05/08
Officer responsible: Bob McLeish
Task completed
Rose Gardens
Action, Reduce size of upper level rose bed and turf / seed remaining area. Remove roses from lower level beds and reuse to fill upper level. Replant lower level beds with Berberis. Prune established shrubs. Officers responsible D. Simpson and Bob McLeish
Broken Fence
Action
Unpainted Fence
Action
Graffiti on Wall
Action, Remove graffiti by 28/04/08
Officer responsible: James Connolly
Task Completed 25/04/08
Rubbish Removal
Damaged Coping
Action: Replace coping by 16/05/08
Officer responsible: Bob McLeish
Task completed
Dumped Rubbish opposite Socks and Slides
Action: Litter control officers to investigate report of person responsible. Debris to be removed by 09/05/08
Officers responsible: David Hay (litter control) and Bob McLeish
Task completed
Roads, Footways and Paths
Dirty Path - Colquhoun Road to Crannog Court
Action: Sweep path by 24/04/08 weedkilling already carried out.
Officer responsible: James Connolly
Task Completed 29/04/08
Rubble behind Fence at Crannog Court
Action: Remove Debris by 09/05/08
Officer responsible: Bob McLeish
Task completed
Right of Way
Action: Meet with Councillor / Community council on site to establish area of complaint. R.O.W inspected on 29/04/08 and was easily accessible.
Officer responsible: D. Simpson
Footways alongside the A82
Action: awaiting lane closure to carry out sweeping.
Officer responsible: James Connolly